Project schedule
Schedule and milestones
The project runs for twelve months, from August 16, 2026 to August 15, 2027.
Research tasks
Month 1 begins August 16, 2026. Month 12 ends August 15, 2027.
| Task | Deliverable | Timing | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. Develop the knowledge base | Knowledge base defining components, stakeholders, and interdependencies | Months 1–3 | ||||||||||||
| 2. Build the conceptual model | Structured conceptual model of the C&D waste management system | Months 4–5 | ||||||||||||
| 3. Develop, validate, and verify the simulation | Working simulation model, validated with historical data and expert input | Months 6–9 | ||||||||||||
| 4. Scenario analysis | Scenario results, data-driven recommendations, and visual outputs | Months 10–12 |
Milestones and deliverables
| Milestone | Due by | Status |
|---|---|---|
| TAG member list | September 15, 2026 | In progress |
| Project website | September 15, 2026 | Complete |
| TAG Meeting 1 | September 15, 2026 | Complete Held September 10, 2026 |
| 1st Quarterly Progress Report | November 15, 2026 | Planned |
| 2nd Quarterly Progress Report | February 15, 2027 | Planned |
| TAG Meeting 2 (project mid-point) | April 15, 2027 | Planned |
| 3rd Quarterly Progress Report | May 15, 2027 | Planned |
| Draft Final Report | July 15, 2027 | Planned |
| TAG Meeting 3 (after the draft final report) | August 1, 2027 | Planned |
| Final Report | August 15, 2027 | Planned |