Project schedule

Schedule and milestones

The project runs for twelve months, from August 16, 2026 to August 15, 2027.

Research tasks

Month 1 begins August 16, 2026. Month 12 ends August 15, 2027.

Research tasks by project month
Task Deliverable Timing 123456789101112
1. Develop the knowledge base Knowledge base defining components, stakeholders, and interdependencies Months 1–3
2. Build the conceptual model Structured conceptual model of the C&D waste management system Months 4–5
3. Develop, validate, and verify the simulation Working simulation model, validated with historical data and expert input Months 6–9
4. Scenario analysis Scenario results, data-driven recommendations, and visual outputs Months 10–12

Milestones and deliverables

Contract milestones
MilestoneDue byStatus
TAG member listSeptember 15, 2026In progress
Project websiteSeptember 15, 2026Complete
TAG Meeting 1September 15, 2026Complete Held September 10, 2026
1st Quarterly Progress ReportNovember 15, 2026Planned
2nd Quarterly Progress ReportFebruary 15, 2027Planned
TAG Meeting 2 (project mid-point)April 15, 2027Planned
3rd Quarterly Progress ReportMay 15, 2027Planned
Draft Final ReportJuly 15, 2027Planned
TAG Meeting 3 (after the draft final report)August 1, 2027Planned
Final ReportAugust 15, 2027Planned